29 November |
Early today the first shipment of new dome parts arrived from MFG/Ratech.
The parts include the new dome base ring, part of the shutter and some lower
dome panels. Some tests of the dome anchor bolts must be done before
assembly can begin. |
|
|
|
Meanwhile we are moving the new earthshine dome out to its foundation.
|
|
|
01 December |
Today the new dome base ring is being put into place. The ring is made of
four sections which are bolted together. The base ring also has the bottom
parts of the new arch girders welded onto it. |
|
|
05 December |
Today the first course of dome panels was finished.
|
06 December |
The MFG/Ratech crew is working on shore today. They are preparing the
dome arch girders and shutter track for installation. The preparation work
is expected to take several days. |
|
|
13 December |
The second row of dome panels is being installed today.
These are the panels with the vent louvers. |
|
|
14 December |
More second-row panels being installed. Here you can
see the motors to control the vents and the anti-bird
grills installed on the inside of the louvers. |
|
|
18 December |
The arch girders are now both in place, and the
third course of dome panels is being installed.
Also the fixed panels between the arch girders have been
installed.
|
|
|
20 December |
The last of the third row of panels are now up. The
MFG/Ratech crew is now attaching a tarp to cover the
shutter opening and the top of the dome. The crew will
return next month to finish the job.
|
|
|
21 December |
The MFG/Ratech crew is securing a tarp on the dome
to cover the top and shutter opening. The crew will
return next month to install the dome top panels,
finish the caulking and install the dome shutter, aperture cover and
motors.
|
|
|
23 December |
More pictures showing the tarp the MFG/Ratech crew placed on
the dome.
|
|
|
|
|
31 December |
It seems all of our plans have come to naught. The tarp was blown off by
high winds on Monday the 26th. There is a storm expected tonight and another one
Monday. Jeff and Randy have arranged tarps inside the dome to direct the
water into the basement, from where it can flow into the lake. All of the
computers in the dome have been turned off in case water does reach them.
|
|
|
03 January |
We had a storm yesterday, with rain, snow and high winds.
The tarp system mostly worked well, but there were a few leaks.
The MFG/Ratech crew has returned to resume work on the dome.
They are starting by drilling the bolt holes in the top panels.
|
|
|
|
|
|
|
04 January |
The MFG/Ratech crew is installing one of the top panels on the dome.
|
|
|
12 January |
The MFG/Ratech crew is installing the first shutter panel.
The telescope will look through this aperture at the Sun.
|
|
|
13 January |
The remaining shutter panels were installed today.
Next job is to install the motors for the shutter and the
dome rotation. Today we tested one of the shutter drive
motors in the lab.
|
|
|
|
|
02 February |
The exterior of the dome is complete except for the
door over the aperture and the skirt to cover the
dome base ring. Conduit is being installed
inside the dome to carry power and control signals to
the louvers The motors for the shutter and dome
rotation and the azimuth drive chain have not yet been
installed. Also changes to the drive chains for the
shutter need to be made.
|
|
|
|
|